International Civil Works Completed

Ghoubet Wind Farm Djibouti Civil Works

OBG's first international project — civil foundation and site works for a 60 MW wind farm on the Gulf of Tadjoura coast, Republic of Djibouti. Sub-contractor to Siemens Gamesa Renewable Energy (SGRE).

0 Installed capacity
0 Contract value
Djibouti Republic
2021–2023 Project duration
Project Overview

Orchid goes international — building Djibouti's wind energy future

The Ghoubet Wind Farm, on the volcanic coastline of the Gulf of Tadjoura, is one of the Republic of Djibouti's most significant energy infrastructure investments — a 60 MW facility that will materially reduce the country's dependence on imported power from Ethiopia.

Siemens Gamesa Renewable Energy (SGRE) was appointed as the engineering, procurement and construction contractor. Orchid Business Group was selected as civil sub-contractor — our first project outside Ethiopia — to deliver the ground-level civil works: wind turbine foundation excavation, mass concrete foundation pours, inter-turbine cable trench and ducting, access road construction between turbine locations, and laydown area preparation for turbine component storage.

Operating in a foreign country for the first time, Orchid mobilised a self-sufficient team to Djibouti — managing customs clearance for our equipment fleet, establishing site logistics in a country without the supply infrastructure we had available in Ethiopia, and integrating with SGRE's international project management systems. The successful delivery of Ghoubet established Orchid as a company capable of operating beyond Ethiopia's borders.

"Ghoubet proved that Orchid can operate on an international stage — working to the quality standards demanded by a European tier-one EPC contractor in a foreign country on a first-time deployment."
— OBG Managing Director
Scope of Work

Three work packages. One renewable energy future.

Orchid's civil scope covered every ground-level work package required to receive and commission the Siemens Gamesa turbines — from formation level excavation through to access roads and laydown areas.

Wind turbines — Ghoubet, Djibouti
01

Wind Turbine Foundation Works

Excavation to turbine foundation formation level, bulk concrete foundation pours to SGRE specification, reinforcement placement and surface finishing — all to the tight tolerances demanded by wind turbine manufacturer specifications and structural engineering certification.

  • Foundation excavation per turbine
  • Bulk concrete pours
  • Rebar placement to SGRE spec
  • Bolt template setting & levelling
Inter-turbine cable trench and ducting — Ghoubet
02

Inter-Turbine Cable Trench & Ducting

Excavation of inter-turbine cable trenches connecting each turbine foundation to the substation, with HDPE conduit installation, backfill and reinstatement — critical for the collection network of the wind farm's electrical system.

  • Cable trench excavation
  • HDPE conduit installation
  • Concrete-encased duct routes
  • Reinstatement to design
Site access roads and laydown — Ghoubet wind farm
03

Site Access Roads & Laydown

Construction of internal site roads between turbine locations for turbine component delivery, and preparation of laydown areas for blade, nacelle and tower storage during erection operations.

  • Crane hardstanding areas
  • Internal access roads
  • Turbine component laydown
  • Compacted gravel surfacing
The Scale

Numbers that define a milestone

60
MW
Installed wind capacity
Reducing Djibouti's power imports
15
M USD
Approximate contract value
Civil sub-contract to SGRE
1st
OBG's first international project
Beyond Ethiopia's borders
2021–23
Project duration
Gulf of Tadjoura, Djibouti
The Challenge

First international deployment in volcanic coastal terrain

New Country

Operating in Djibouti for the first time required establishing supply logistics, customs clearance procedures and accommodation in an unfamiliar environment with limited existing supply chain.

Volcanic Rock

The Ghoubet site is composed of hard volcanic basalt presenting drilling and foundation excavation challenges requiring heavy breakers and controlled blasting.

SGRE Standards

Siemens Gamesa's construction quality requirements and documentation standards are set to European engineering norms — significantly more demanding than Ethiopian project documentation norms.

Our Approach

Preparation, integration and execution

Advance Reconnaissance

Three months before mobilisation, Orchid's project management team conducted a full site and logistics assessment in Djibouti — identifying supply sources, customs requirements and accommodation before a single machine moved.

Heavy Rock Breaking

Additional hydraulic breaker attachments deployed specifically for the Ghoubet volcanic basalt — ensuring foundation excavation productivity matched the SGRE programme.

Embedded QC Team

A dedicated quality coordinator embedded within SGRE's project QMS from day one, ensuring all foundation and civil works were documented to the European standard required for turbine erection sign-off.

Resources Deployed

Built for hard ground, tight spec

Orchid deployed a self-sufficient plant fleet to Djibouti — all customs-cleared and mobilised from our own owned asset base.

Excavators with hydraulic breakers

Hydraulic breaker attachments for hard volcanic basalt excavation to turbine foundation formation level

Concrete mixers & transit trucks

Ready-mix delivery for mass turbine foundation concrete pours to SGRE specification

Drilling rigs for anchor bolts

Precision anchor bolt drilling through reinforced foundation concrete to turbine manufacturer specification

Vibratory rollers

Compaction of internal access road formation and laydown areas to specified bearing capacity

Motor graders

Formation grading and shaping of inter-turbine access roads and crane hardstanding areas

Cable trenching equipment

Chain trenchers and backfill equipment for inter-turbine cable routes and HDPE duct installation

Ghoubet Wind Farm — completed turbines, Gulf of Tadjoura
Orchid's plant fleet — customs-cleared and fully operational on the Gulf of Tadjoura
Project Timeline

From contract award to turbine sign-off

2021

Contract Award, Djibouti Mobilisation & Customs Clearance

Sub-contract awarded by SGRE. Advance logistics reconnaissance, equipment customs clearance and site establishment on the Gulf of Tadjoura coastal site.

2022

Foundation Excavation & Concrete Works, Cable Trenching

Systematic turbine foundation excavation through volcanic basalt, mass concrete foundation pours, rebar placement and anchor bolt setting. Inter-turbine cable trench excavation and HDPE conduit installation.

2023

Site Roads, Laydown Areas, QC Sign-off & Demobilisation

Completion of internal access roads and crane hardstanding areas. SGRE quality sign-off on all foundations. Final as-built documentation submitted. Full equipment demobilisation to Ethiopia.

Client & Partners

Delivering for a European-standard principal

Électricité De Djibouti (EDD)

State energy utility and project owner. EDD is responsible for Djibouti's electricity generation and distribution, and is the off-taker for Ghoubet's 60 MW output.

Project Owner

Siemens Gamesa Renewable Energy (SGRE)

Leading European wind turbine manufacturer and EPC contractor. Appointed as principal for the Ghoubet Wind Farm under a full EPC contract with EDD and the Republic of Djibouti.

EPC Contractor & OBG Principal

Orchid Business Group PLC

Ethiopia's specialist infrastructure contractor, engaged as civil sub-contractor for turbine foundation works, cable trenching, access roads and laydown areas — OBG's first international deployment.

Civil Sub-Contractor
Have a project in mind?

Let's build something
remarkable together.

From feasibility through final handover — Orchid Business Group brings the machines, the manpower and the mastery.

Chat with us!