Pile Foundation Bridge Works Completed

SATCON Gambella Three River Bridges

Bored pile foundations for three bridge substructures in Gambella Region, western Ethiopia — OBG's most remote piling project in the country's tropical lowlands, sub-contracting to SATCON Construction.

3 Bridges
Gambella Region
SATCON Sub-Contract
Completed Status
Project Overview

Pile foundations for three river crossings in Ethiopia's tropical west

Gambella Region, in Ethiopia's tropical far west, is one of the country's most remote and access-challenged regions — cut off by seasonal flooding from the Baro River and its tributaries, with high rainfall, dense vegetation and roads that disappear in the rainy season. Three bridge structures were required to provide reliable year-round connectivity across major river crossings.

SATCON Construction PLC was appointed as main contractor for the three bridge projects. Orchid Business Group was engaged as piling sub-contractor — responsible for bored cast-in-situ pile foundations at bridge abutments and mid-river piers. The Gambella assignment was Orchid's most remote active piling project, requiring complete self-sufficiency in a region with almost no local construction supply infrastructure.

"Gambella is one of the most logistically challenging environments in Ethiopia — getting a Bauer rig there, keeping it fuelled and supported, and drilling to specification while managing groundwater — is a genuine achievement."
— OBG Project Director
Scope of Work

Two specialist work packages. Three remote river crossings.

Each bridge required a fresh site establishment along the regional road corridor — repositioning the Bauer rig and re-establishing the bentonite system at each new abutment and pier location.

Bauer rig at Gambella bridge abutment piling
01

Bridge Abutment & Pier Piling — 3 Crossings

Bored cast-in-situ pile foundations at abutments and mid-river piers for three separate river crossing structures — each requiring the Bauer rig to be repositioned and a new site established along the regional road corridor.

  • 3 separate bridge locations
  • Abutment & pier piles
  • Alluvial soil drilling
  • Bentonite-supported boreholes
Temporary casing installation in Gambella alluvial soils
02

Tropical Groundwater Management

High groundwater tables throughout the Gambella alluvial plain required continuous bentonite slurry management and full temporary casing to pile toe — preventing borehole collapse in the saturated tropical soils.

  • Full temporary casing to depth
  • Bentonite slurry management
  • Dewatering of pile cap excavation
  • Wet season coordination
The Scale

Numbers that define the project

3
River Bridge Foundations
Three separate crossings
700+
km
From Addis Ababa
Ethiopia's most remote piling project
2020
Year completed
All three bridges delivered
Gambella
Ethiopia's tropical west
Baro River basin lowlands
The Challenge

Remote tropical piling with seasonal flooding risk

Extreme Remoteness

Gambella is 700+ km from Addis Ababa by road, with limited fuel, no spare parts availability and transport restricted to 4WD in wet season. Orchid required complete self-sufficiency for months on site.

Wet Season Risk

Gambella's tropical rains flood the working areas completely. All pile installation had to be completed before the rains and resumed only after water receded.

Soft Alluvials

Gambella's river plains are composed of very soft, waterlogged alluvial deposits with no bearing capacity until significant depth — making full-depth temporary casing essential for borehole stability.

Our Approach

Self-sufficiency, wet season planning and alluvial drilling expertise

Forward Operating Base

Orchid established a dedicated camp at Gambella with 3-month fuel and spare parts inventory, generator power and vehicle workshop — maintaining operational independence regardless of road conditions.

Dry Season Priority

All pile drilling and concrete works completed in dry season windows. Wet season used for temporary works and site preparation.

Full Bentonite System

Complete bentonite mixing, recirculation and recycling system deployed — managing fluid losses in the porous alluvial soils and maintaining borehole stability to pile toe.

Project Timeline

From advance reconnaissance to final demobilisation

2018

Contract, Advance Reconnaissance & Mobilisation Convoy

Contract awarded by SATCON. Advance team reconnaissance of all three sites. Mobilisation convoy of Bauer rig, bentonite plant, camp equipment and support fleet despatched from Addis Ababa to Gambella — 700+ km.

2019

Bridge 1 & 2 Piling — Dry Season

Bored pile installation at abutments and piers for Bridge 1 and Bridge 2 completed during the dry season window. Full temporary casing and bentonite management throughout. Concrete cast by tremie to all pile toes.

2020

Bridge 3 Piling, QC & Demobilisation

Bridge 3 pile installation completed. Full quality control documentation submitted to SATCON and Ministry of Transport. Equipment demobilisation convoy returned to Addis Ababa. Project formally closed.

Client & Partners

Delivering for Ethiopia's west

Ministry of Transport, Ethiopia

Federal ministry responsible for transportation infrastructure investment across Ethiopia — commissioning the Gambella bridges to improve regional connectivity.

Owner

SATCON Construction PLC

Ethiopian contractor appointed as main contractor for the three Gambella bridge structures — engaging Orchid Business Group as specialist piling sub-contractor.

Main Contractor

Orchid Business Group PLC

Specialist piling sub-contractor delivering bored cast-in-situ pile foundations at all three bridge abutments and mid-river piers across the Gambella corridor.