22.6 km of new road through the highlands of SNNPR — Orchid Business Group delivered full road construction for the Ethiopian Roads Authority in Southern Ethiopia.
The Sawla–Kako road connected two communities in the SNNPR highlands, providing an all-weather road where previously only dry-season tracks existed. For the Ethiopian Roads Authority, this was a critical last-mile connectivity project for a region with some of Ethiopia's poorest access to markets, health facilities and schools.
Unlike Orchid's sub-contract work at GERD and Addis–Adama, Sawla–Kako was a direct ERA contract — placing Orchid as primary contractor responsible for design-to-specification delivery and all element management across the 22.6 km route through hilly terrain with significant cut-and-fill, multiple culverts and drainage structures. Five years on site reflected the careful, layer-by-layer approach required on a hillside road through expansive clay soils — demanding close moisture control to prevent future pavement failure. The completed road opened year-round access for communities previously isolated during the rainy season.
"Roads like Sawla–Kako are the backbone of rural Ethiopia — connecting communities to markets, schools and health centres. Their construction requires patience, precision and deep knowledge of local ground conditions."
— Ethiopian Roads Authority
The Sawla–Kako contract covered the full spectrum of rural road construction — from initial formation earthworks through pavement construction to drainage and culvert installation.
Full route formation through undulating highland terrain — extensive cut-and-fill with weathered basalt, laterite and expansive clay soils requiring careful moisture conditioning before compaction, with GPS-controlled grading to design level throughout.
Sub-base and base layer construction using imported gravel and crushed stone, followed by gravel wearing course — providing a durable, maintainable surface for rural traffic volumes. CBR-tested materials throughout.
Comprehensive drainage including side drains, mitre drains, catch drains and precast concrete culverts at all watercourse crossings — critical for road longevity in a high-rainfall SNNPR environment.
SNNPR's highland soils include significant proportions of expansive black cotton clay — swelling on wetting and shrinking on drying, causing pavement failure if not carefully managed at sub-grade level.
SNNPR's heavy monsoon rainfall turns unpaved access routes impassable for months, requiring careful wet season planning and sequence management across the full 22.6 km.
All materials and equipment had to be hauled over long distances on existing rough tracks, with fuel, parts and supplies managed from Addis Ababa throughout five construction seasons.
Expansive clay sub-grade treated with lime to reduce plasticity index and achieve stable compaction — a technique rarely applied on rural roads in SNNPR at the time.
All earthworks, compaction and gravel surfacing prioritised in October–April dry season windows, with wet season time used for culvert and drainage structure construction.
Borrow materials sourced from approved local quarries wherever feasible, reducing haulage distances, managing costs and supporting the local economy throughout the programme.
Site establishment, route survey, access establishment and pioneer clearance. Initial earthworks commenced on the southern end of the alignment.
Full formation earthworks across the route. Lime stabilisation applied to expansive clay zones. GPS-controlled grading to design level.
Sub-base and base layer using CBR-tested gravel and crushed stone. Layer-by-layer compaction and testing across the full 22.6 km.
Gravel wearing course applied along the full route. Drainage completion including side drains, mitre drains and outfall structures.
Final inspection with ERA, defects rectification and formal handover. Road opened to all-weather traffic for communities along the Sawla–Kako corridor.
State body responsible for the construction and maintenance of Ethiopia's federal road network. Project Owner and Employer on the Sawla–Kako Road.
Project Owner & EmployerEthiopia's specialist infrastructure and earthworks contractor, engaged as primary contractor for the full 22.6 km Sawla–Kako road construction under a direct ERA contract.
Primary Contractor — Road ConstructionFrom feasibility through final handover — Orchid Business Group brings the machines, the manpower and the mastery.